I'd like to list the things that need to get done so that we can get to the point where the PPC platforms are part of the standard release.
What I have on the list so far is
- Release machines. Need an additional LE and BE machine to be used for releases only
- Additional test machines. Need to have 2 LE and 2 BE machines, currently there is only 1 of each
- Need to add testing on PPC to node-test-pull-request
- Tests passing (they all do now except for test-tick-processor (test-tick-processor failures on PPC node#2957)
Can people chime in on what else I'll need to add to this list.